🌍 All Study Guides📊 Dashboard📰 Blog💡 About
Google Project Management Professional Certificate • STUDY MODE

TIME ESTIMATION

QUESTION 1 OF 59

What are some resources you can consult to find tasks to add to a project plan? Select all that apply.

A
Customer surveys
B
Project plans used in the past for similar projectsCorrect Answer
C
Relevant work documents, like emails or meeting notesCorrect Answer
D
The project charterCorrect Answer
Explanation:

These are some of the items you can consult to identify project tasks. Explanation: This is one of the items you can consult to identify project tasks.

QUESTION 2 OF 59

Which of these tasks might you identify from your Sauce & Spoon menu tablets project charter? Select all that apply.

A
Add a reservation booking feature to the tablets
B
Implement a post-dining survey to assess customer satisfactionCorrect Answer
C
Train management, FOH staff, and BOH staffCorrect Answer
D
Install tablets in the bar areas at the Downtown and North restaurant locationsCorrect Answer
Explanation:

As a core deliverable of the project, this is one of the tasks that might be identified from the project charter. Explanation: As a core deliverable of the project, this is one of the tasks that might be identified from the project charter. Explanation: As a core deliverable of the project, this is one of the tasks that might be identified from the project charter.

QUESTION 3 OF 59

Which of the following tasks from the historical project plan could be helpful for the tablet project? Select all that apply.

A
Test out reservation systems
B
Create contracts and statements of work for vendorsCorrect Answer
C
Generate quotes and review costsCorrect Answer
D
Create a launch day plan: staffing, troubleshooting, etc.Correct Answer
Explanation:

The tablet project likely involves working with external vendors, so this is a task you can pull from the historical project plan. Explanation: Generating quotes and reviewing costs ensures that a project stays within budget, so this is a task you can pull from the historical project plan. Explanation: The tablet project needs a launch day plan, so this is a task you can pull from the historical project plan.

QUESTION 4 OF 59

Which of the following project tasks can you identify from the email exchange about tablet logistics? Select all that apply.

A
Train general managers how to enter payroll
B
Schedule an electricianCorrect Answer
C
Connect the Sauce & Spoon marketing team with Terrific Tablets for brandingCorrect Answer
D
Train the staff to update the menuCorrect Answer
Explanation:

This is one of the tasks you can identify from the email exchange. ACTIVITY: IDENTIFY PROJECT TASKS: CONDUCT ONLINE RESEARCH

QUESTION 5 OF 59

How does domain knowledge help project managers with new projects? Select all that apply.

A
Makes them experts in a given industry and types of projects in that industry
B
Means they don’t need to know anything about an industry in order to work in it
C
Provides information about a given industry and types of projects in that industryCorrect Answer
D
Saves time on future projects within that industryCorrect Answer
Explanation:

This is one of the ways domain knowledge helps project managers.

QUESTION 6 OF 59

Imagine you come across the following information in your online research: “Our restaurant keeps our devices safe by always locking them up at the end of service, and making sure we keep track of them at all times.” What tasks could you create from this finding that would help with the tablet rollout project? Select all that apply.

A
Upgrade the restaurant)s security system
B
Run tests on the tablet software
C
Enable GPS location services on each tabletCorrect Answer
D
Create a procedure for securing tablets at the end of the night (at the table or in a safe)Correct Answer
Explanation:

Enabling GPS services could be part of the tablet configuration process, so this task would help with the project. Explanation: Creating a procedure to secure tablets could be part of the staff training, so this task would help with the project.

QUESTION 7 OF 59

Imagine you come across the following information in your online research: “Tablets increase customer confidence that their credit card information won’t be stolen when they understand that transactions take place through a secure portal at the table.” What tasks could you create from this finding that would help with the tablet rollout project? Select all that apply.

A
Encourage all customers to use cards even when seated at tables without tablets
B
Partner with a credit card company to offer discounts
C
Include payment security talking points in waitstaff trainingCorrect Answer
D
Create messaging about payment portal security to display on the tabletsCorrect Answer
Explanation:

Payment security talking points could be part of the staff training, so this task would help with the project. Explanation: Creating messaging about tablet security could be part of the tablet configuration process, so this task would help with the project.

QUESTION 8 OF 59

What are the benefits of providing accurate time estimates for individual tasks? Select all that apply.

A
They enable you to avoid purchasing expensive project management software.
B
They establish a better sense of the overall project timeline.Correct Answer
C
They help you accurately track task progress.Correct Answer
D
They help you predict if a milestone may go over a deadline.Correct Answer
Explanation:

By adding up each task’s duration, you get an informed idea of when you and your team will complete the project. Accurate estimates also clarify if a milestone may go over deadline and help to track task progress. Explanation: Knowing tasks’ time estimates allows you to better understand how far along a team is with a particular phase of a project. Accurate estimates also help to establish a better sense of the project timeline and clarify if a milestone may go over deadline. Explanation: If a milestone is likely to go over an important deadline, you can quickly make adjustments to the size of the tasks or team members) workloads to fit within a required deadline. Accurate estimates also help to establish a better sense of the project timeline and track task progress.

QUESTION 9 OF 59

As a project manager, you try to get an accurate time estimate for a task by communicating with an expert. After considering their time estimate, you are unsure if it includes all steps of a task, so you ask them to explain each step in detail. What strategy for getting an accurate time estimate did you choose?

A
Assess the expert’s confidence level in their estimate.
B
Ask the expert how likely they think it is that an assumption might not work out and how it would affect their estimate.
C
Check the expert)s understanding of the task.Correct Answer
D
Check the expert’s estimates against the actual time spent on similar tasks in previous work.
Explanation:

You won’t include every detailed step in the project plan, but it may help the expert come to a time estimate by thoroughly explaining each step in a task.

QUESTION 10 OF 59

As a project manager, you try to get an accurate time estimate for a task by communicating with an expert. After receiving their time estimate, you ask questions like, “What equipment do you suppose you’ll have?” and “How many people do you expect to work on the task?” What strategy for getting an accurate time estimate did you choose?

A
Assess the expert’s confidence level in their estimate.
B
Ask the expert how likely it is that assumptions they have might not work out and how it would affect their estimate.
C
Check the expert’s estimates against the actual time spent on similar tasks in previous work.
D
Discuss the assumptions the expert may be making when they give an estimate.Correct Answer
Explanation:

Asking the expert about their specific assumptions can help uncover areas where they may be misguided in the project.

QUESTION 11 OF 59

As a project manager, you try to get an accurate time estimate for a task by communicating with an expert. You ask them to think back to a task that resembles the one for this project and describe what was the same, what was different, and if thinking about this previous task changes their estimate. What strategy for getting an accurate time estimate did you choose?

A
Discuss the assumptions the expert may be making when they give an estimate.
B
Ask the expert how likely they think it is that their assumptions might not work out and how it would affect their estimate.
C
Check the expert’s estimates against the actual time spent on similar tasks. (CORRRECT)
D
Check their understanding of the task.
Explanation:

You can estimate task time by reviewing the time it took an expert to complete a similar task on a previous project.

QUESTION 12 OF 59

What type of time estimate considers how long it takes to complete a task, plus the time it takes to test the product?

A
Effort estimate
B
Total duration estimateCorrect Answer
C
Timeline estimate
D
Conservative estimate
Explanation:

There are two types of time estimates: effort estimates and total duration estimates. The main difference between effort estimate and total duration estimate is adding time for factors such as prep, approvals, and testing. ACTIVITY: IDENTIFY TIME ESTIMATES FOR YOUR PROJECT PLAN

QUESTION 13 OF 59

Peta spoke with Seydou about how long it would take for the tablets to arrive. What are some risks that might affect the time estimate for shipping and receiving the tablets? Select all that apply.

A
A repair fee to fix broken devices
B
Tablets shipping with outdated software
C
A shipping delayCorrect Answer
D
Broken devices (CORRRECT)
Explanation:

Seydou indicates that a shipping delay of 2-3 days is unlikely, but possible, so it could affect this time estimate. Explanation: Terrific Tablets occasionally ships broken devices, which could affect this time estimate.

QUESTION 14 OF 59

Peta spoke with Deanna about how long it should take to finalize menu items and coupon values. What are some risks that might affect the time estimate for uploading menu and coupon content? Select all that apply.

A
Waitstaff have not yet been trained to use the tablets
B
Restaurant customers are not interested in coupons
C
Carter’s schedule can be unpredictableCorrect Answer
D
Carter wants to revamp the menu before he finalizes the menu and coupon informationCorrect Answer
Explanation:

It could take Carter a few days to a few weeks to revamp the menu, so this is a risk that might affect this time estimate. Explanation: Depending when Carter finishes the menu revamp, it might affect this time estimate.

QUESTION 15 OF 59

Peta spoke with Seydou about how long it would take to integrate the tablets with Sauce & Spoon’s POS system. What are some risks that might affect the time estimate around POS integration? Select all that apply.

A
The updated POS software has a yearly licensing fee
B
The waitstaff hasn’t been trained on the tablets yet
C
Sauce & Spoon may not be running version 3.0 of their POS softwareCorrect Answer
D
Sauce & Spoon may need to update their POS systemCorrect Answer
Explanation:

If the tablets aren’t compatible with the software, it could affect the tablet integration estimate. Explanation: If Sauce & Spoon needs to update their software, it could affect the tablet integration estimate.

QUESTION 16 OF 59

Based on the tablet shipping estimate transcript, what time estimate is appropriate for the tablet shipping schedule?

A
5 days
B
3 days
C
10 daysCorrect Answer
D
14 days
Explanation:

Since shipping should take about a week, and a 2-3 day delay is possible, this is a reasonable time estimate.

QUESTION 17 OF 59

Based on the scheduling software installation transcript, what time estimate is appropriate for the software installation schedule?

A
5 days
B
10 days
C
7 days
D
3 daysCorrect Answer
Explanation:

The update could take a few days, but the integration should only take a few hours, so this is a reasonable time estimate. ACTIVITY: ADD CONFIDENCE RATINGS

QUESTION 18 OF 59

The meeting notes state that training will happen in two phases—one for managers and one for staff. Which of the following three-point time estimates would you choose for fully training the team (including planning, training the managers, and training the staff at each location)?

A
Optimistic: 2 days; Most Likely: 1 day; Pessimistic: 4 days
B
Optimistic: 15 days; Most Likely: 30 days; Pessimistic: 45 days
C
Optimistic: 10 days; Most Likely: 14 days; Pessimistic: 21 daysCorrect Answer
D
Optimistic: 20 days; Most Likely: 14 days; Pessimistic: 10 days
Explanation:

Since the meeting notes mention separate training sessions for managers and staff, this is a reasonable three-point estimate.

QUESTION 19 OF 59

Which of the following pieces of information should Peta consider when determining the confidence rating for the wiring time estimate? Select all that apply.

A
The team is still waiting for the menu update
B
The team)s level of confidence in the time estimateCorrect Answer
C
The electrician is confident in the amount of time they need to complete the wiringCorrect Answer
D
The restaurant has attempted table wiring at least once beforeCorrect Answer
Explanation:

The team’s level of confidence in the estimate should impact the confidence rating. Explanation: The electrician)s opinion should impact the confidence rating. Explanation: The restaurant’s past experience with similar tasks should impact the confidence rating.

QUESTION 20 OF 59

The meeting notes state that Sauce & Spoon has never integrated tablet software with their POS system before and may need to upgrade the system before starting the integration. What confidence rating is appropriate for the POS system time estimates?

A
High
B
Medium
C
LowCorrect Answer
Explanation:

Sauce & Spoon has no experience integrating tablet software with their POS system, so the confidence rating should be Low.

QUESTION 21 OF 59

The meeting notes state that the electrician could complete the wiring for both locations in two business days (or 16 hours). Because the restaurants cannot close for a full day for the upgrade, the team estimates four business days (two half-days at each location) to complete the wiring. Based on this information, what notes could you make to add context for this task in the project plan? Select all that apply.

A
“Find money in the budget for an electrician”
B
“Contact internet service provider to ensure the network can handle tablet WiFi traffic"
C
“Notify GMs when their locations need to close for wiring”Correct Answer
D
“Check with electrician on whether mornings or afternoons work better with their schedule”Correct Answer
Explanation:

Based on the information, this is a useful note to add to the project plan. Explanation: Based on the information, this is a useful note to add to the project plan.

QUESTION 22 OF 59

Which documentation can a project manager review to uncover project tasks? Select all that apply.

A
Project schedule
B
Project charterCorrect Answer
C
Emails that relate to the projectCorrect Answer
D
Previous project plansCorrect Answer
Explanation:

To uncover tasks, you can review the goals and deliverables in the project charter and list all the items that have tasks or milestones associated with them. Other helpful documentation for uncovering tasks includes old project plans and emails that relate to the project. Explanation: Relevant emails can help you uncover tasks and identify team members to connect with if you have questions. Other helpful documentation for uncovering tasks includes project charters and old project plans. Explanation: Previous project plans can provide inspiration as you create a list of tasks. They can also help you identify task durations, subject matter experts, and suppliers. Other helpful documentation for uncovering tasks includes project charters and emails that relate to the project.

QUESTION 23 OF 59

Fill in the blank: _____ refers to knowledge of a specific industry, topic, or activity.

A
Domain knowledgeCorrect Answer
B
Project knowledge
C
Milestone knowledge
D
Stakeholder knowledge
Explanation:

When unfamiliar with a new project’s domain, you may need to analyze supporting documentation to help broaden your knowledge.

QUESTION 24 OF 59

As a project manager, what steps can you take to identify tasks through conversations with your project team? Select all that apply.

A
Share your list of tasks in collaboration software and hope the team offers insights.
B
Brainstorm as a group with team members who will likely work on those tasks.Correct Answer
C
Leverage the expertise of teammates to help fill in the gaps in your list of tasks.Correct Answer
D
Hold one-on-one conversations with team members to discuss tasks they will be responsible for.Correct Answer
Explanation:

One step you can take is to brainstorm with the group. Beyond that, you can hold one-on-one conversations with team members to discuss the tasks they will be responsible for and leverage the expertise of your team members to help fill out your list of tasks Explanation: Experts on your team and in your organization can offer helpful insights. Beyond that, you can hold one-on-one conversations with team members to discuss the tasks they will be responsible for and brainstorm as a group with team members who will likely work on these tasks. Explanation: As a project manager, it can be helpful to hold one-on-one conversations. This can clarify the project tasks each team member will likely be responsible for. Beyond that, you can brainstorm as a group with team members to discuss their tasks and leverage the expertise of team members to help fill out your task list.

QUESTION 25 OF 59

What is the right level of detail for each item in your list of tasks?

A
Tasks should have the level of detail that is requested by the project’s high-influence stakeholders.
B
Tasks should be detailed enough that your role as a project manager is no longer relevant and the team can manage itself.
C
Tasks should be detailed enough that you are able to check in on progress and identify problems early on.Correct Answer
Explanation:

Tasks should be detailed enough that you can monitor progress and identify challenges. It is also important that tasks are not so detailed that you)re endlessly revising your project plan and constantly asking for team updates.

QUESTION 26 OF 59

Which of the following are techniques to identify milestones? Select all that apply.

A
Identify the easiest tasks and batch them together.
B
Identify tasks that carry a high risk.Correct Answer
C
Identify points in the project plan where you and your team can evaluate the work completed so far.Correct Answer
D
Identify tasks that signal the completion of a project phase or major task.Correct Answer
E
Identify important tasks that your stakeholders have a particular interest in.Correct Answer
Explanation:

You may want to identify tasks with high risk, such as a test, as a milestone. Explanation: These types of milestones may be the same as some of your deliverables. Explanation: You may want to consider these tasks as a milestone because they have a major impact on the project’s overall progress. Explanation: To do this, review your notes from previous conversations with stakeholders. Identify tasks that stakeholders were eager to know more about or wanted to review when complete.

QUESTION 27 OF 59

Which of the following are strategies for getting accurate time estimates from your task experts? Select all that apply.

A
Ask for time estimates after the team completes its work so the expert can consider team performance.
B
Ask for estimates of the substeps and make note of them.Correct Answer
C
Discuss the assumptions the expert makes when they give you an estimate.Correct Answer
D
Check their understanding of the task.Correct Answer
E
Compare the experts’ estimates against the actual time spent on similar tasks in previous work.Correct Answer
Explanation:

To get accurate time estimates, you can ask for substep estimates and add them up to affirm total time needed to complete a task. You can also check an expert’s understanding of the task and discuss their assumptions. Finally, you can compare expert estimates against the actual time spent on similar tasks in previous work. Explanation: You can discuss an expert’s assumptions and ask them to consider how likely it might be that these assumptions impact the estimate. You can also check an expert’s understanding of the task and ask for estimates of the task’s substeps. Finally, you can compare expert estimates against the actual time spent on similar tasks in previous work. Explanation: One strategy is to ask an expert to explain all the detailed steps involved in the task to think through the work involved. You can also ask for estimates of task substeps and discuss the expert’s assumptions. Finally, you can compare expert estimates against the actual time spent on similar tasks in previous work. Explanation: Ask the expert to think about a similar project they worked on and describe what was different and what was the same. You can also check an expert’s understanding of the task and ask for estimates of the task’s substeps. Finally, discuss an expert’s assumptions and ask them to consider how likely it is they will impact the estimate.

QUESTION 28 OF 59

Which three calculations does a project manager use when doing a three-point estimate?

A
Least likely
B
OptimisticCorrect Answer
C
PessimisticCorrect Answer
D
Most likelyCorrect Answer
Explanation:

Three-point estimating helps to determine the most realistic time estimate for a task. It uses optimistic, most likely, and pessimistic calculations. Together, these offer a clearer sense of what)s possible with each task. Explanation: Three-point estimating helps to determine the most realistic time estimate for a task. It uses optimistic, most likely, and pessimistic calculations. Optimistic and pessimistic calculations are based on the best-case and worst-case scenarios. Explanation: Project managers can use three-point estimating to help determine the most realistic time estimate for a task. The estimate is based on optimistic, most likely, and pessimistic calculations.

QUESTION 29 OF 59

As a project manager, a team member gives you a time estimate that’s different from what you hoped for. You ask the team member to provide neutral information, such as research findings, to support their estimation. Which time estimation negotiation technique did you use?

A
Focus on interests, not positions.
B
Present mutually beneficial options.
C
Insist on objective criteria.Correct Answer
D
Say “no” without saying “no.”
Explanation:

This technique gets the team member to remove any biases in their estimation and rely on objective information.

QUESTION 30 OF 59

In addition to avoiding distractions, which of the following are ways to bring empathy to conversations? Select all that apply.

A
Observe and frequently remind people of the work they)ve been assigned.
B
Connect with people’s experience.Correct Answer
C
Recognize buffering.Correct Answer
D
Listen with curiosity.Correct Answer
E
Repeat what you think you heard.Correct Answer
F
Recognize judgments.Correct Answer
Explanation:

You can demonstrate empathy by trying to connect with another person’s experience and making it clear that you want to support their work. You should also listen with curiosity and repeat what you think you heard. Finally, you need to recognize your own judgments and ask about time buffers. Explanation: A helpful way to practice empathy is to recognize buffering and encourage team members to open up about any extra buffer time they add to estimates. You should also listen with curiosity, repeat what you think you heard, and connect with the experience of the person you’re talking with. Finally, it is important to recognize your own judgments. Explanation: You should listen with curiosity and ask questions to demonstrate your interest in what people have to say. You can also repeat what you think you heard and connect with the experience of the person you’re talking with. Finally, you should try to recognize your own judgments and ask about time buffers when discussing estimates. Explanation: To encourage empathy, you can restate the message of the person you are talking to in your own words. You can also listen with curiosity and connect with the experience of your team members. Finally, you should try to recognize your own judgments and ask about time buffers. Explanation: One approach to embracing empathy is to recognize your judgements and try to put yourself in the other person’s position. You should also listen with curiosity, repeat what you think you heard, and connect with the experience of the person you’re talking with. You also need to ask about time buffers.

QUESTION 31 OF 59

One of the deliverables in your project involves marketing your new product with email blasts. Your team writes several drafts of the different marketing materials, generates an email list, and programs the emails to be sent on the correct dates. Which of the following represents a milestone in your project plan?

A
Targeted email lists are generated.
B
Marketing materials are drafted.
C
Emails are programmed to be sent on the correct dates.
D
Marketing emails are sent on scheduled dates.Correct Answer
QUESTION 32 OF 59

You are developing a schedule for your team’s project plan. Why might you ask your stakeholders or colleagues to share with you emails that relate to the project?

A
These emails can help you uncover tasks.Correct Answer
B
These emails tell you what your team members are doing.
C
These emails can help you bond with your colleagues.
D
These emails will keep you involved with every aspect of the project.
QUESTION 33 OF 59

You start a new job as a project manager in the private banking industry. You need to have a basic understanding of topics such as how clients open accounts, back office operations, and how trade confirmations are verified. Which of the following terms refers to the knowledge you need?

A
Intellectual property
B
Enterprise learning
C
Competitive intelligence
D
Domain knowledgeCorrect Answer
QUESTION 34 OF 59

You need to reach out to a high-influence stakeholder for help in identifying project tasks. You gather as much information as possible and outline clear questions for the stakeholder. Why is it important to complete this prep work before your conversation?

A
This preparation reveals the skill gaps within your team.
B
This preparation demonstrates your independence.
C
This preparation demonstrates your respect for your stakeholder’s limited time.Correct Answer
D
This preparation will answer your questions without having to meet with the stakeholder.
QUESTION 35 OF 59

You have gathered information from project documentation and the project team. With this information, you identified and created a list of tasks for your project plan. What is the next step for completing your project plan?

A
Identify points in the project plan where you can evaluate completed work.
B
Identify tasks that stakeholders have a particular interest in.
C
Identify the order in which tasks need to be completed.Correct Answer
D
Identify tasks that carry a high risk.
QUESTION 36 OF 59

Which of the following may indicate a milestone for your project?

A
A task that has a major impact on the project)s overall progressCorrect Answer
B
A task that your team has the most experience with
C
A task that has the highest confidence ratings
D
A task that involves the fewest dependencies
QUESTION 37 OF 59

What term refers to a time estimate that accounts for factors like getting approvals, prep work, testing, and so on?

A
Effort estimate
B
Total duration estimateCorrect Answer
C
Milestone estimate
D
Taskflow duration estimate
QUESTION 38 OF 59

You are making time estimates for your project plan. You ask your task expert to estimate how long the task would take if you assume you need to replace your vendor and you experience unexpected turnover right before the task begins. Which of the measures involved in “three-point” time estimations are you asking from your task expert?

A
Pessimistic time estimatesCorrect Answer
B
Planning time estimates
C
Milestone time estimates
D
Most likely time estimates
QUESTION 39 OF 59

Which of the following circumstances is likely to cause a low confidence rating for a task?

A
It is a task that involves only one team member.
B
It is a task that your team has never done before.Correct Answer
C
It is a task that was completed quickly during past projects.
D
It is a task that takes a long time to complete.
QUESTION 40 OF 59

Which of the following is a good way to bring empathy to a conversation?

A
Keep the conversation brief.
B
Listen with curiosity.Correct Answer
C
Keep the conversation focused and on point.
D
Start by clearly stating your position.
QUESTION 41 OF 59

What is the purpose of your project plan?

A
To keep your project on trackCorrect Answer
B
To identify milestones
C
To document scope
D
To determine tasks
QUESTION 42 OF 59

Which of the following terms refer to knowledge of a specific industry, such as industry terms, techniques, and processes?

A
Competitive intelligence
B
Enterprise learning
C
Intellectual property
D
Domain knowledgeCorrect Answer
QUESTION 43 OF 59

When populating your project plan with a set of tasks, when is the best time to hold a group brainstorming session with team members to help identify tasks? Select all that apply.

A
After brainstorming a task list with senior stakeholders
B
Before you do any other project work
C
After you research your project onlineCorrect Answer
D
After you review project documentationCorrect Answer
QUESTION 44 OF 59

Which of the measures involved in “three-point” time estimations express how long you hope the task will take, assuming everything goes as planned?

A
Planning time estimates
B
Milestone time estimates
C
Most likely time estimates
D
Optimistic time estimatesCorrect Answer
QUESTION 45 OF 59

Your team is building a website that will consist of four new pages of content. Your project plan has two team members work together to deliver one page of content: one will outline page content while the other does mockups of page layout. Then they will work together to produce the completed page. Which of the following represents a milestone in your project plan?

A
A completed mockup of page layout
B
A completed page of contentCorrect Answer
C
A completed outline of page content
D
A completed project plan
QUESTION 46 OF 59

To identify project tasks for your project plan, you review project documentation and research your project online. You have connected with members of your project team and other experts in your organization to examine your list of tasks. You decide you need additional details about a key deliverable. Who should you speak to in order to receive the missing information?

A
Your company’s most senior project manager
B
Your company’s Chief Operating Officer
C
Your most senior stakeholder
D
One of your high-influence stakeholdersCorrect Answer
QUESTION 47 OF 59

Determining the proper task order will help you assign start and end dates for each task. When determining task priorities, what should you consider first?

A
The basic order of operationsCorrect Answer
B
The target date for completing the project
C
The number of team members available for the project
D
Which team members will address each task
QUESTION 48 OF 59

You estimate time requirements for designing and launching a new page on the company website. Your page designer estimates that they can design and build a page for launch in three days. You determine that you will need an additional two days for copy editing, legal clearance, and launch authorizations. What is the effort estimate for this task?

A
Eight days
B
Three daysCorrect Answer
C
Five days
D
Two days
QUESTION 49 OF 59

Why is the three-point time estimating technique a good way to determine a confidence rating for your time estimates?

A
It ensures you have considered the best-case and worst-case conditions for a task.Correct Answer
B
It is the time estimating technique that involves input from the most people.
C
It removes all uncertainty from your estimate.
D
It is a commonly used technique that everyone is familiar with.
QUESTION 50 OF 59

When you ask questions of your team members without showing empathy, you can leave them feeling too closely observed, controlled, or continuously reminded of the work they have been assigned. What is the term that expresses this negative impact your team members feel in this case?

A
Harassment
B
Justifying
C
MicromanagingCorrect Answer
D
Arguing
QUESTION 51 OF 59

You are managing a construction project and must pour the foundation before you can move on to the building phase of your project. You have ordered the required materials, selected the best team members to execute the pouring, and scheduled a day to when the foundation will be poured. Which of the following represents a milestone in your project plan?

A
Scheduling a day to pour the foundation
B
Receiving required materials
C
Completing the foundationCorrect Answer
D
Selecting team members
QUESTION 52 OF 59

You have created an ordered list of tasks for your project plan. What is the next step for identifying milestones?

A
Identify tasks that can be completed most quickly.
B
Identify alternative orderings for your list of tasks.
C
Identify additional tasks for your project plan.
D
Identify points in the task list where you can evaluate work completed so far.Correct Answer
QUESTION 53 OF 59

When identifying a project milestone, which of the following describes what you are seeking?

A
The last task in your project plan
B
Tasks that signal customer payments are due
C
Tasks that signal the completion of a project phaseCorrect Answer
D
The first task in your project schedule
QUESTION 54 OF 59

What is a negative impact of micromanaging?

A
It demonstrates a manager)s lack of trust and confidence in the people they oversee.Correct Answer
B
It demonstrates doubt about the value of the project.
C
It causes stakeholders to doubt your ability to manage your team members.
D
It causes the manager to worry more.
QUESTION 55 OF 59

One of the tasks in your project involves setting up the stage for a talent show. Before the team can do this, you need estimates from an audiovisual contractor, and the construction crew needs to build the stage backdrop. What term refers to these preliminary needs?

A
Task dependenciesCorrect Answer
B
Project scope
C
Milestones
D
Vendors
QUESTION 56 OF 59

You start a new job as a project manager in an industry that is unfamiliar to you. Which of the following are examples of domain knowledge that you will need to have a basic understanding of? Select all that apply.

A
Industry market performance
B
Industry competitors
C
Industry processesCorrect Answer
D
Industry termsCorrect Answer
QUESTION 57 OF 59

What term refers to a time estimate that only takes into account the actual time it takes to complete a task?

A
Taskflow duration estimate
B
Effort estimateCorrect Answer
C
Milestone estimate
D
Total duration estimate
QUESTION 58 OF 59

As a project manager, you determine your time estimate confidence ratings. You notice that your confidence is low across a large percentage of task estimates. Who is the most important person to communicate your uncertainty about the project timeline to?

A
Your project stakeholdersCorrect Answer
B
Your team member that you are least confident in
C
Your manager
D
Your team members
QUESTION 59 OF 59

Which of the measures involved in “three-point” time estimations is based on how long the task usually takes under normal circumstances, with only slight adjustments to the best-case scenario?

A
Planning time estimates
B
Pessimistic time estimates
C
Optimistic time estimates
D
Most likely time estimatesCorrect Answer

Ready to test your recall?

What are some resources you can consult to find tasks to add to a project plan? Select all that apply.

💡Select all 3 correct answers before submitting (0 of 3 selected).
A
Customer surveys
B
Project plans used in the past for similar projects
C
Relevant work documents, like emails or meeting notes
D
The project charter

How confident are you in this answer?